|
African Energy Legacy Projects
[last updated February 13, 2006 9:42 AM]
Shortcuts:
|
![]() |
Partnership website(s) |
Expected TimeframeJanuary 2003 - December 2010 |
Governments:
|
Major Groups:
|
UN System:
|
Other intergovernmental organizations:
|
| Other:
|
Primary Themes:
|
Secondary Themes:
|
Geographic Coverage
Geographic Scope: Regional
Country(ies) where the partnership is being implemented: Angola, Democratic Republic of the Congo, Kenya, Malawi, Mozambique, Namibia, South Africa, United Republic of Tanzania, Zambia |
National Focal Points
This partnership has not made any contact with the national focal points for sustainable development in the countries involved
|
Partnership targetsTo complete the Western Corridor scoping study by December 2002, with full implementation by 2010.
To construct 200km of 220kV transmission line between Matambo Substation (Tete, Mozambique) and a substation north of Blantyre, Malawi by 2005. To construct 370km of 330kV transmission line between Nairobi (Kenya) and Arusha (Tanzania) as well as 670km of 330kV transmission line between Mbeya (Tanzania) and Pensulo (Serenje, Zambia) by 2005. To refurbish the Zongo and Sanga hydroelectric facilities in order to restore their generation capacity from 17MWe to 87MWe. To interconnect the two facilities (12km), refurbish the transmission system for power delivery to Kinshasa and repair the access roads. |
Progress against targetsProgress relating to each of the projects listed above, as at January 2006, is:
? Significant progress was made in the Western Corridor Project (WESTCOR), through the signing of the inter-government and inter-utility agreements to co-develop the project. The five participating utilities (BPC, ENE, Eskom, NamPower and SNEL) have each committed USD 100 000 to be used for the funding of the feasibility studies for this project. A shareholders agreement was signed at the end of 2005 such that each participating utility agreed to own 20% of Westcor. The Westcor project includes the development of a 3 500 MW hydro power plant on the Congo River (Inga III - first phase), the development of the Western Corridor (DRC-Angola-Namibia-Botswana-RSA power transmission line), and the associated telecommunications infrastructure. The Westcor accounts were opened in Gaborone, Botswana, including a project office. Westcor is now in the process of appointing the Chief Operations Officer for the Head Office in Botswana. ? To construct 200km of 220kV transmission line between Matambo Substation (Tete, Mozambique) and a substation north of Blantyre, Malawi by 2005. In 2004, HCB of Mozambique won a tender for the supply of 200MW (maximum) power to ESCOM Malawi. Preliminary and environmental studies have been completed. ESCOM Malawi is in the process of finalising the power purchase agreement which will support bankability and financing. The final financing decision will be made during 2006. ? To construct 370km of 330kV transmission line between Nairobi (Kenya) and Arusha (Tanzania) as well as 670km of 330kV transmission line between Mbeya (Tanzania) and Pensulo (Serenje, Zambia) by 2005. Power generation capability within Kenya has been affected, due to the severe drought conditions experienced, over the last couple of years. Thus it is likely that the Tanzania-Kenya interconnector would be constructed first with the sole aim of supplying power to Kenya. Agreements have been signed between both parties. As of last year, the economic analysis for the Zambia-Tanzania interconnector was still pending. Further, there have been changes in Tanzania that have called for a review of the interconnector studies. Tanzania has discovered gas deposits and would have to compare the cost of power from possible CCGT power stations in Tanzania to the cost of importing hydropower from SAPP via Zambia. Due to the above developments, the Zambia-Tanzania interconnector may take longer than initially planned. . ? To refurbish the Zongo and Sanga hydroelectric facilities in order to restore their generation capacity from 17MWe to 87MWe. To interconnect the two facilities (12km), refurbish the transmission system for power delivery to Kinshasa and repair the access roads. ? Studies and site investigations have indicated that this project is not feasible. |
Coordination Mechanism of the PartnershipProgress on the initiative is being tracked by the Coordinating Centre for the Southern African Power Pool and regular updates can be made available.
The Western Corridor is the subject of an inter-utility MoU that provides for the establishment of a joint venture company for implementation. Current activities are coordinated through a Steering Committee consisting of the Chief Executive Officers of the four utilities involved. The implementation and operation of the remaining interconnectors could be funded by the World Bank, the individual utilities or through a special purpose company, in which several stakeholders may choose to participate. |
Implementation Mechanism of the PartnershipFrom NEPAD perspective therefore, regionally viable projects are proposed in the following context of developing a pan African Transmission Grid and the hydro resources of the Inga river as follows:
* Eastern transmission corridor development through the completion of the SAPP interconnection network to Tanzania and Malawi, and further extention of the SAPP grid to eastern Africa trough an HV Tx line from Arusha in Tanzania to Nairobi in Kenya. * The above Tx projects will, in the short term, enable the wheeling of power from existing excess capacity markets (RSA, Zambia, Mozambique and DRC), to existing capacity-short markets (Tanzania, Malawi, Kenya). * In the medium to long term horizon these lines will enable the delivery of power from future rehabilitated and newly developed hydro resources in the DRC, Zambia and Mozambique to Eastern Africa including Kenya, Sudan, Ethiopia and Arithrea. * As a second development phase it is proposed to further develop the enormous and stable hydro power resources of central Africa through the rehabilitation of existing plants like the Inga 1 and 2, which will add about a 1000 MWe, and the development of new greenfield plants like the Inga 3 (1500-3500 MWe). In the medium to long term horison it is proposed to develop the 40 000-50 000 MWe hydro-power potential of the Grand Inga. * However major transmission lines will be required to wheel the Inga power to the Southern, eastern and South African markets. It is therefore proposed to reinforce and upgrade the eastern corridor HV Tx line from DRC to Zambia and to develop the DRC-Angola-Namibia-South Africa Tx line (the "Western Corridor"). * In conjunction with the large scale development of the hydro resources of central and southern Africa, it will be necessary to upgrade the Transmission line from DRC (Inga) to Zambia and to develop the Western transmission corridor from Inga in the DRC through Angola, Namibia, Botswana to South Africa. * In terms of the development of a continental grid it is important to create a link between the Southern African Power Pool (SAPP) and the West Africa Power Pool (WAPP). This will require the developing of a DRC-Congo Brazzaville- Gabon-Equatorial Guinea- Cameroon-Nigeria HV Tx line. * Another (direct) connection to Eastern Africa market is proposed to be developed by a HV Tx line from the Inga to Uganda. * In the medium to long term horison it is proposed to link the Inga to Cairo by an HV Tx line from Nigeria, or Cameroon via Chad, Libya and Egypt. * However, with a view to build-up investor confidence in this part of the continent, it is proposed to embark on a smaller size rehabilitation project of an existing 95 MWe hydro plant at Zongo and Sanga site which, in the short term, will provide a reliable power supply to Kinshasa and Brazzaville |
Funding Currently AvailableAmount in US$: 0
Source(s): IGO
Total investment for the four components outlined above are estimated at US$ 800 million. World Bank has committed to undertaking some aspects of this (Mozambique-Malawi interconnection and the feasibility study for the Tanzania-Zambia interconnection). |
Non-financial resources availableType(s):
Source(s):
|
Funding SoughtRequired Amount in US$: not specified
Source(s) already approached: In the case of the Western Corridor, it is expected that all four utilities would contribute equity and take shareholding in the joint venture company. It is envisaged that the Zongo-Sanga refurbishment could be funded through a joint venture between Eskom Enterprises and Nampower International. Further partners are invited to express their interest.
|
Non-financial resources soughtRequirement(s):
Source(s) approached and details:
|